CET Electric Cost Effectiveness Output Day Shifting Correction Update

The CET currently contains a known issue in the day-shifting calculation logic that has impacted electric cost effectiveness outputs since its release in August 2025.


The issue impacts the following ELECTRIC cost effectiveness outputs:

  • TSB

  • TRC

  • PAC

  • RIM

  • SCT

The issue does not impact:

  • Savings outputs (kW, kWh, Therms)

  • GHG outputs (CO2, NO2, PM-10)

  • Gas cost effectiveness outputs

The Energy Division is currently working with the PAs and consulting teams to finalize and test a correction. At this stage, we anticipate an update release within the next week.

Additional communication will be provided as testing and release timing are confirmed.

Select the module in CEDARS
Select user type
Status: In Progress1 comment

This request was merged into another request

Comments1

  • cedars team

    Team•

    Jun 4

    IOU first round of testing complete, testing has been extended to REN/CCAs. Avoided Cost data corrections will be available on cedars-2 tomorrow.