Budget Filing PGE 2026 Goal Attainment Summary - TSB Filing amount wrong
Jake:
PG&E’s goals are correct in CEDARS-2, but the filing values are not. For example, 2026 has 268M TSB (see below by just taking the C&S off the bottom table), but the filing amount shows 204M. Same issue in production.
- Select the module in CEDARS
- Select user type
Log in to comment and vote
Comments4
cedars team
Nov 5, 2025
@JakeRichardson can you clarify the values you are expecting to see in the Goal Attainment summary?
Jake Richardson (PG&E)
Nov 5, 2025
Our excel appendix shows them in Tables 2.1a and 2.2a
https://cedars.cpuc.ca.gov/documents/download/3544/mainchange_summary%7Cmain%7Credline)/
cedars team
Nov 6, 2025
Hey @JakeRichardson the dashboards are now showing the correct numbers. Could you confirm if this ticket is now complete. Thanks.
Jake Richardson (PG&E)
Nov 6, 2025
agreed, values are correct.