In comparing CEDARS results for Program Segment Summary with SDGE internal system, we noticed that the CE Ratio values are elevated for CEDARS in both the dashboard and as a table download.

Elevated values exist for TRC, PAC, and RIM as noted below in the orange fields representing CEDARS.

Status: Completed5 comments

Log in to comment and vote

Comments5

  • cedars team changed status to In Testing
    Team•

    Oct 8, 2025

    Pinned

    Hey @ggreen the updated dashboard values are now ready for review on cedars-3. Please let us know if they are what you would expect. Thanks, Sonja

  • Jennifer Scheuerell

    Team•

    Sep 29, 2025

    Hi @ggreen Thanks for your patience, we are internally testing this fix now and expect to have it live on cedars-2 for you to retest on Weds.

    • ggreen

      •

      Oct 7, 2025

      Is this still something that is planned for deployment? I’m still seeing the same elevated ratios in Staging. These same results are also being reflected in Production too.

      • Jennifer Scheuerell

        Team•

        Oct 7, 2025

        Yes, the fix for this is up on cedars-3 right now if you can please take a look there and let us know any feedback @ggreen

  • ggreen

    •

    Sep 24, 2025

    Also, ‘SCT Base’ and ‘SCT High’ values are not included in the table download (appear on dashboard only).