MCE EE Portfolio Dashboard Feedback
In the Cost Effectiveness tab the Forecasted values for Commercial on CEDARS2 shows 1.06 but CEDARS shows 1.14, Cross Cutting 0.35 v 0.41.
Some values in the budget and expenditures tab are off by 1 (most likely some rounding issue).
- Select user type
Log in to comment and vote
Comments6
Oct 29
PinnedClosing this ticket as an updated EE dashboard is due to be published in production this evening.
Yamini
Oct 30
Thank you for the comment! This is now corrected on CEDARS2:
2026 Forecast is now showing:
Commercial TRC - 1.14
Cross-Cutting TRC - 0.35
klarsonRRN
Oct 30
Thank you!
cedars team
Oct 14
Hi @KLarsonTCR could you confirm if the problem you are seeing is on the URL supplied on this ticket https://cedars-2.cpuc.ca.gov/reports/metrics-and-indicators/all/
Or this feedback is actually meant for EE dashboard?
klarsonRRN
Oct 14
This was for the EE Dashboard/PowerBI.
klarsonRRN
Oct 12
This is for MCE. My username changed.