Custom memo area, modeled similarly to ex-ante memos, to capture guidance for early opinions.

Select the module in CEDARS
Select user type
Status: In Testing1 comment

Log in to comment and vote

Comments1

  • cedars team

    Team•

    Oct 29

    We’re still waiting on final requirements from the Custom team. They plan to review their proposed approach with CPUC tomorrow afternoon (Oct 30) and expect to send a final response by end of day.

    Timeline impact:

    • Interim deadline moved from Nov 11 to Nov 18. The Custom team has agreed to the one-week extension.

    • The plan assumed we’d have everything we need to start development by Monday (Nov 2). If the response is delayed, or the final details change any assumptions we’ve made, we may need more time.

    • Dec 4 is still the target for a fully populated Custom Resources tab.